Flowchart of installing charger for new energy electric vehicle
Step 1: Site Visit
Step 1: Site Visit
Our team arranges electrical engineering technicians to visit the parking lot (to inspect the parking space). According to the actual situation, they evaluate whether the parking space and electrical equipment are suitable for installing an electric vehicle charger.
Step 2 : Quotation and Order Confirmation
Step 2 : Quotation and Order Confirmation
After our electrical engineering technicians complete the site inspection, they will prepare a quotation according to the installation requirements and give it to the customer for confirmation, and a deposit is required.
Step 3 : Preparation of Installation Plan
Step 3 : Preparation of Installation Plan
After we receive the deposit from the customer, our electrical engineering technicians will tailor-make the relevant installation project plan and charger installation drawings according to the (site inspection) situation. The relevant application documents require the customer to authorize the electrical engineering technicians to apply on their behalf.
Power engineering technicians assist customers in applying for electricity meters
We assist applicants to submit the electrical installation project plan and charger installation drawings to the housing estates to which they belong.
After we receive the client's documents, we submit them to the housing estate to which they belong. It takes about 3-5 working days to get the result.
(Depending on the approval progress of individual housing estates)
Step 4 : Payment of deposits to CLP
Step 4 : Payment of deposits to CLP
In response to the situation of individual housing estates, it is necessary to apply for independent electricity meters from China Light and Power Company or Hong Kong Electric Company for new energy equipment. We assist customers in applying for electricity meters. Generally, we notify customers through the email address provided by the customer and receive a notice from the power company to pay the deposit.
Step 5 : Scheduled Reservation Installation
Step 5 : Scheduled Reservation Installation
We will install power lines, switches and chargers according to the plans and drawings within the scheduled installation date arranged by the customer or the building management office.
Step 6 : Appointment of CLP service
Step 6 : Appointment of CLP service
Our power engineering technicians make an appointment with the power company to turn on the power (hang the meter)
The new energy electric vehicle charger device can only be used after the electricity meter is installed by CLP or HK Electric.
Step 7 : WR1 Completion Certificate issued upon completion of installation
Step 7 : WR1 Completion Certificate issued upon completion of installation
The power company dispatches engineers to inspect and test the charging device to ensure it meets safety standards, and issues a certificate of installation completion letter WR1, indicating that the project has been completed.
Step 8 : Final payment to us
Step 8 : Final payment to us
After the watch is installed, the customer needs to arrange to pay the remaining balance to the company.
A. EHSS 屋苑及已有電力設備 費用HKD$ 2800 (單相 / 三相 )
包括:由註冊電工技術人員安裝掛牆鑽孔、由獨立開關電制至機身入線箱包5米電線、代辦電力公司申請掛錶和代辦電力裝置改動完工紙(WR1)和監察
B. 獨立屋及村屋 費用HKD$ 4800 (單相 / 三相 )
包括:由註冊電工技術人員安裝掛牆鑽孔、由獨立開關電制至機身入線箱包10米電線、代辦電力公司申請掛錶和代辦電力裝置改動完工紙(WR1)和監察
C.工商廈/機構 費用HKD$ 6800 (單相 / 三相)
包括:由註冊電工技術人員安裝掛牆鑽孔、由獨立開關電制至機身入線箱包15米電線、代辦電力公司申請掛錶和代辦電力裝置改動完工紙(WR1)和監察
其他額外服務費用如下:
1. 額外拉線單相($300/米) / 三相($350/米)
2. 額外安裝防水箱 $2800
3. 高空工作 (另議)
4.保養並不包括因錯誤安裝而導致的損壞 (如需上門檢查:$1800/日)